Posted on: May 23, 2017

Saratoga Drainage Improvements

Over the past 12 months D.N. Higgins has been installing drainage improvements within your neighborhood. The drainage work is near completion and the final phase of work is scheduled to begin on Tuesday, May 30, 2017.  Mail service, garbage collection service and driveway access will continue to be maintained during the last stage of construction.   

The final phase involves removing the existing roadway surface. Prior to re-paving the roadway, the road will be a drivable rock base material that will be primed and sanded to minimize tracking.  If material is tracked onto your driveway the Contractor will remove tracked material from the driveway at the end of the project.  

Based upon the Contractor’s schedule the final phase will be completed in approximately 45 days.  The Contractor will begin work on minor roads and work towards major roads to lessen the impact to the community.  Below is the order roadways will be reconstructed in: 

1) Churchill Drive

2) Gulfstream Circle

3) Suffolk Drive

3) Laurel Way

3) Lexington Drive

4) Saratoga Blvd

 If any special accommodations are required please contact the Engineering Office at (561)790-5131.

Facebook Twitter Google Plus Email

1050 Royal Palm Beach Blvd.
Royal Palm Beach, FL 33411
Ph: (561) 790-5100
Fx: (561) 790-5174
Home   Contact Us   RSS   Accessibility    Privacy Statement   Copyright Notice   Sitemap   Powered by CivicPlus